The Ministry of Public Works/Bahamix, has scheduled Milling and Paving works for Bernard Road from 9:30a.m. to 2:00p.m., Monday through Friday, beginning September 19th 2018, for 21 working days.
The resurfacing of Bernard Road will extend from the “Village Rd/Wulff Rd/Soldier Rd Junction” to the Roundabout at Fox Hill Freedom Park.
Bernard Road will be divided into eight (8) paving sections to minimize traffic congestion. The paving Sections are listed below:
Wulff/Village/Soldier - Thompson Street
Thompson Street - Hillside Park Road
Hillside Park Road - Windsor Street
Windsor Street – Adderley Street
Adderley Street – Grant Street
Grant Street – Cockburn Street
Cockburn Street – Rahming Street
Rahming Street – Fox Hill Roundabout
There will be east and west bound lane closures implemented for the sections and for the duration of the works. Traffic diversions will be put into effect for each “section”.
Provisions will be made for residents and businesses where necessary. Motorists are asked to avoid the area if possible.
You are asked to be aware of and acknowledge the posted traffic paving signs in the area.
If you have any queries or concerns, please feel free to contact us at telephone numbers (242) 361-3886 or (242) 341-3886.
Bahamix apologizes for any inconvenience caused.