 CEO Press Statement on Generation
CEO Press Statement on Generation 
		 
	
Good Afternoon Ladies and Gentlemen of the Press
	
First we wish to recognize that there exists a perception that our performance as it relates to communication has been not been what it should be. That is one aspect of the current situation that we must take 100 percent responsibility for.
	
However, while we may not have communicated the reality of the situation well, communication is not what got us to where we are.  
	
	
To a large extent the complexities that led us to where we are have also contributed to our inability to both relieve our consumers and communicate definitive answers as they relate to load shedding.
	
We will attempt to give more clarity this afternoon.
	
Secondly, we do not intend to assign blame as that is now irrelevant. The blame game does not offer relief nor does it lend to solving the problems we are faced with.  It is important however to come to grips with how we got to where we are.
	
It must be noted that the Board appointed in 2017 and this current Board have had a collective stint of just over 24 months. Those two Boards met the following set of circumstances in place:
	
•    A decaying generation fleet, with equipment up to 60 years old.
•    A generation fleet where parts could no longer be procured or could only be procured exclusively from manufacturers that have not been very responsive to our requests for help.
•    A generation fleet where preventative maintenance was not the order of the day.
•    A generation fleet that relied on costly fuel.
A generation fleet that, if action were not taken quickly, could in fact lead us to where we are today or worse.
Neither the time frame between those two boards, nor the circumstances that may have led to the change in Boards, had an impact on that history.
	
We had hoped that with the help of the additional rental units from Aggreko, we would be in a position to prevent load shedding for the summer. While we were certainly cognizant of the tightrope we were walking, due to the pressure being placed on the remaining plant, we did not anticipate this level of systems failure and even if we had, we would not have had the resources to mitigate the situation as this level of accelerated decay could not be anticipated.
	
So here is where we are:
	
Our peak demand is 250MW.We have a total of 210MW available today, which includes the following:
	
•    105 MW in Aggreko rental capacity,
•    35 MW at Clifton Pier, and
•    70 MW from Blue Hills.
	
This equates to 210MW or 40MW short of what is required, hence the load shedding. We are working feverishly on returning two generators at Blue Hill Power Station that will make up this 40MW difference. However, we cannot guarantee that other units will not fail and return us to load shedding as we have no excess capacity. As we get deeper into the Fall, the demand will drop off as will the need for load shedding.  
It is important to understand that BPL employees have been extremely supportive and working diligently during this entire ordeal. It would have been equally appreciated if the same level of support was received from engine manufacturers who have not been so responsive to our repeated requests for help. 
	
	
We are extremely aware that our consumers’ patience has long run out and that confidence in what we are telling you is low.  But it is the truth. 
	
	
It is an ugly truth that the inheritors of the truth must tell and that no amount of editorials, political bombast, and armchair quarterbacking can change. 
While our existing generation fleet has been in decay, load in New Providence has consistently grown with many new mega complexes. We are building a new 132MW plant, as seen today, but regretfully the acceleration of the decay has created a gap and resulted in the circumstances we are all experiencing.
	
The men and women at BPL are working tirelessly to reduce that gap, but only so much can be done with the existing infrastructure, where no parts are available and even the manufacturers have offered little to assist.  A lot of mistakes were made in the past and we are now the ones that must carry the load. So be it. 
	
	
We do not expect the inconvenienced public to be sympathetic.  All we can do is work diligently to resolve the issue once and for all.  We wish the public to be aware that every waking hour is being spent on ensuring that the plan for the long term solution is being adhered to, while at the same time we are attempting to reduce the pain that is being felt in the short term.
	
This team is confident that those that follow us – our consumers, the management and staff of BPL – will never have to endure that which we have had to endure for the past 40 plus years.
	CHAIR Press Statement on Generation 
	
	
Ladies and gentlemen of the press, good afternoon.
	
The
 Board of Directors of Bahamas Power and Light Company Limited is 
cognizant of the challenges faced by Bahamians due to prolonged load 
shedding and lingering problems with power generation. We know the 
problems it is causing for homes, and for businesses, for industry, and 
for families. I want to again apologize to our customers and The 
Bahamian people for not providing the level of service that should be 
expected from a national electrical utility. We intend to do all we can 
as quickly as possible to resolve the issues that inhibit our ability to
 provide the quality of service all of our customers deserve.
	
While
 Mr. Heastie focused on generation and other critical operational 
issues, a different perspective on the challenges facing BPL is that as a
 company, we have been disadvantaged by decades of nonalignment of 
strategic vision for the company and the needs of our growing customer 
base. As more housing developments were being constructed, more resorts 
and other foreign direct investments were courted and constructed, as 
the economy and the population has continued to grow, there should have 
been concurrent investments in increasing generation capacity to 
sufficient levels that would ensure the company’s ability to meet 
growing demand and sufficient headroom to allow for redundancy. That 
nonalignment is equally at play in our challenges, and perhaps more 
significant than the current shortfall in generation, in our view.
	
The
 facts are plain: decisions that would have obviated the problems we 
face today were not made, and so we are here, challenged to fix these 
problems once and for all. But as a board, we are committed to doing 
exactly that, and not making excuses or placing blame.
	
The
 mandate given to this board by the Government of The Bahamas is to fix 
the issues that plague our national electricity company once and for 
all. We are not here to kick the can down the road, or to implement 
temporary or Band-Aid solutions. We are here to address the structural 
problems facing BPL head on, and to stay focused until those problems 
are resolved, and we can present The Bahamian people with an electrical 
utility that delivers on its mandate to provide safe, reliable, and 
affordable electricity to all its customers. The Board is providing 
diligent oversight of a strategic plan that we believe will achieve this
 stated goal.
	
Despite the reality we currently 
face, we are not without optimism. We believe that our current strategic
 plan with a phased approach for execution, will allow us to achieved 
measured and objective improvements in our operations, address 
challenges that have been plaguing the company for years, and the 
successful completion of each phase of our plan will allow BPL to 
re-build trust with our customers. 
	
	
The 
completion of the 132 Megawatt power plant at Station A before the end 
of this year is the first phase of our Generation turnaround strategy.  
This Station A power plant is intended to be incorporated into the power
 generation facilities that will be developed and operated by Shell 
North America.  In fact, immediately after the fire in Station C that 
consumed about 65MW of BPL’s generation assets, Shell North America was 
directly involved in the selection of Wartsila to build this power plant
 with the understanding that these engines would become part of the 
larger 220MW generation facility that they will own and operate. Any 
suggestion or assertion that Shell North America has not been involved 
in this process is factually incorrect.  The Station A power plant is 
the largest single plant ever built in the history of the company, it 
will allow us the ability to address some of the generation issues 
mentioned earlier, as well as allow BPL to better prepare to serve its 
customers in summer 2020 and beyond.
	
The 
completion of a second Gas-To-Power Plant by Shell North America will 
mark the completion of the second phase of our Generation turnaround 
strategy, which will see another 90+ megawatts of high-efficiency, 
low-emissions generation pumping power to the grid by mid-2021. 
	
	
Phase
 three of the turnaround for generation is the completion of the 
Terminal Facility for LNG Regasification, which is expected to be fully 
operational by December 2021. With the completion of this facility, the 
Shell power plant as well as BPL’s remaining generation assets will have
 access to LNG, and our customers will immediately see the benefits of a
 cleaner, less expensive, and more environmentally sustainable fuel 
source as the foundation of our energy supply in New Providence.
In
 addition to traditional power generation facilities, we are excited 
about our push into renewables. Over the next four years we will be 
releasing renewable energy generation RFPs for New Providence and all 
the Family Islands. The first of these RFPs have already been issued, 
inviting qualified organizations to submit proposals as Independent 
Power Producers (IPPs) to develop, finance, build, own, and operate a 
solar PV and energy storage plants, or hybrid power plants on Bimini, 
Andros, Eleuthera, and Inagua. BPL intends to leverage what we learn 
from these initial projects to ensure that our implementation of 
renewable energy is done in the most efficient and cost-effective 
manner, with the ultimate goal of providing maximum benefits to our 
customers. 
	
	 
Our strategic push into renewables 
will have a marquis kickoff with work set to begin on implementing the 
new solar energy solution on Ragged Island. As we are all aware the 
Government of the Bahamas made a commitment to make Ragged Island a 
green island, and BPL is doing its part in making this happen. Our team 
visited Ragged Island this past Friday to view sites for the new solar 
plant installation on that island. We are excited about this first solar
 and battery storage solution implemented by BPL, which is paving the 
way for the company in the renewables arena, particularly with regard to
 solar generation. BPL intends to do everything we can to deliver solar 
power to Ragged Island by December of 2019.
We have a plan 
to fix BPL: we have laid out the broad strokes of the plan, and we 
encourage our consumers to hold us accountable. This is our commitment 
to The Bahamian people, and we will stand by it.
	
I
 would like to say clearly: we, the Board of Directors, have absolute 
confidence in the executive team led by Mr. Whitney Heastie to get the 
job done. We support Mr. Heastie’s operational plan, and we stand by his
 team’s ability to bring that plan to fruition.
	
We
 are committed, as a board, to provide strategic oversight of the 
direction in which BPL is heading, and we are excited and open to 
collaborate with all stakeholders on the new strategic direction for the
 company. We firmly believe in this phased approach to resolving our 
Generation challenges once and for all.
	
Today 
we are discussing how we plan to resolve our generation issues, however 
our strategic plan is broader than generation alone; it also addresses 
stabilizing our finances, upgrading our neglected Transmission and 
Distribution network, significantly improving the quality of our 
customer service, building additional capacity within our workforce via 
structured training and certification programs, and above all  keeping 
safety as our first priority both in the workplace and in the services 
we deliver to our customers. We strongly believe that successful 
execution of our strategic plan will allow BPL to provide reliable, cost
 effective electricity that will be viewed as a game-changer with 
respect to its long term positive effect on the growth and development 
of the Bahamian economy.
	
So once again, as a 
Board we have a mandate: fix the problems at BPL once and for all. We 
are committed to doing this. We have confidence in the BPL team, and are
 committed to doing all that we can to ensure that they have all the 
resources required to execute this plan. We, the Board, will hold them 
accountable for success, even as we are held accountable by our 
stakeholders – the public who own this utility.
	
Thank you.